Refurb Week 5
This week there is an update on the filter refurb. Whilst painting it after theĀ old pipework had been removed, it was discovered that the original legs to the vessel had rusted through! Nothing is too much trouble for the GRC Filtration lads, so after a…
Our Story, Pool Update, Refurbishment
Refurb Week 4
No new firms or areas of work to report on this week. The great work already commenced by JCS fabricating the boiler pipework and Aqua Tilers in the pool is continuing. (200 tiles replaced and a few metres of expansion joint removed so far!) The…