Refurb Week 12
We had another delivery of donated paint this week, thanks to the generosity of Brewers Decorator Centres Ltd. We’ve now got the means to decorate the internal doors and other wood work around the building, stamping our identity onto the place. Paul from Aquatilers is back…
Refurb Week 10
The wonderful, we are calling them the “Limescale Ladies” Vicky Fairey, Diane Tuck and Anna Dousek continued their tireless efforts, begun by Jo and Ben Willis, to eradicate the limescale in both shower rooms this week. The task proved more testing than first thought but after…
Refurb Week 11
The painting of the foyer and reception has continued this week. It looks like three coats will be required after all. Luckily, thanks to the Wickes Community Programme there is plenty. The “Limescale Ladies” Anna and Vicky were back descaling and making a fantastic job of…
Refurb Week 9
Welwyn Garden Alarm’s engineer Dylan was on site this week as promised, addressing the intruder alarm. They have kindly donated a new system which has both extended the coverage and reduced the likelihood of false activations. Many thanks to the boss Peter Goodchild for getting…
Refurb Week 8
Quite by fortuitous chance whilst JCS were on the roof wrestling with the flue lining this week, local chimney specialists Tim’s Chimneys got in touch through Facebook wondering if they could lend a hand in any way. The offer was gratefully taken up and they have…
Refurb Week 7
We were delighted that our second volunteer day on 12th July was as well attended as the first with some 30 people giving up their time. Together they sanded, unscrewed, unblocked, filled in and deconstructed all around the building, laying the way open to applying…
Refurb Week 6
The major event this week is that our friends at Dr Heating have, as anticipated, completed the works necessary for the new water main connection to be made They were ably assisted by superstar farmers Ian and Steve (who drove the digger) who between haymaking and harvesting,…
Refurb Week 5
This week there is an update on the filter refurb. Whilst painting it after the old pipework had been removed, it was discovered that the original legs to the vessel had rusted through! Nothing is too much trouble for the GRC Filtration lads, so after a…
Refurb Week 4
No new firms or areas of work to report on this week. The great work already commenced by JCS fabricating the boiler pipework and Aqua Tilers in the pool is continuing. (200 tiles replaced and a few metres of expansion joint removed so far!) The…
Refurb week 3
As planned, work on the pool hall began this week. The guys from Blackrock Scaffolding arrived and under the close supervision of Bobetta, speedily took down the temporary handrails around the pool allowing our new friends Paul and Simon from Aqua Tilers Ltd to make a start….
Recent Comments
Archives
- November 2026
- October 2026
- September 2026
- August 2026
- July 2026
- June 2026
- May 2026
- February 2026
- November 2025
- September 2025
- August 2025
- June 2025
- April 2025
- March 2025
- February 2025
- December 2024
- November 2024
- October 2024
- September 2024
- August 2024
- July 2024
- June 2024
- May 2024
- April 2024
- March 2024
Categories
- Client story (2)
- Fundraising (24)
- Inspiration (2)
- Newsletter (6)
- Our Story (39)
- Pool Update (35)
- Refurbishment (22)